Who this checklist is for (and why you should trust a guy who screwed up)

I've been coordinating off-grid solar and RV power orders for six years. In that time I've personally made—and documented—nine significant mistakes totaling roughly $4,700 in wasted budget. Wrong inverter sizes, missed surge protection, that one time I ignored a flashing error code for three weeks and cooked a $380 charge controller.

My team now uses the checklist below to catch those same problems before they happen. This isn't theory. Every step came from something going wrong on a real job site.

Here's what you need to know: this checklist works whether you're setting up a van, a travel trailer, or a small off-grid cabin. It covers six steps. I'll walk you through each one—what to do, what I did wrong, and the checkpoint that keeps you out of trouble.

Step 1: Do a load calculation before you order anything

When I first started building RV solar systems, I assumed bigger inverter equals better. More power, more headroom, right? Three burned-out AGM batteries later, I learned the hard way that oversized inverters on undersized battery banks are a disaster waiting to happen.

Here's what to actually do:

Calculate your daily watt-hour usage first. Every device, every hour it runs. A 15-amp fridge cycling 8 hours per day draws about 1,400 watt-hours. Add your phone chargers, laptop, lights, water pump. That number determines everything else.

For a typical van or small travel trailer, you're looking at 1,500–3,000 Wh per day. That tells you:

  • Panel size: Roughly 300–600W of solar to replenish daily
  • Battery bank: Lithium or AGM, sized at 2x your daily usage minimum
  • Inverter capacity: Match to your peak load, not your total usage

Growatt inverters are popular for this segment because they cover the range from 1kW to 12kW with built-in MPPT controllers. The mistake I made in 2020 was ordering a 5kW inverter for a system that only had 200Ah of lead-acid storage. The inverter worked fine. The batteries couldn't keep up. Replaced both within a year.

Checkpoint: Before you buy anything, write down your daily watt-hour total and your peak simultaneous load. If the numbers look close, round up on the battery bank, not the inverter.

Step 2: Download the Growatt app before you mount the inverter

This one sounds too simple to mess up. I still messed it up.

In September 2022, I mounted a Growatt inverter in a client's trailer, wired everything, buttoned up the compartment, and drove off. Two days later the client called saying the system wasn't reporting data. The inverter was working—it was charging and inverting just fine—but the WiFi dongle hadn't been configured. And since I'd already sealed the compartment, I had to go back and reopen everything to reset the dongle.

That cost me $180 in travel time and a lot of goodwill.

Now I do this before the inverter goes anywhere near a mounting point:

  1. Download the Growatt ShinePhone app on the phone I'll be using for setup
  2. Plug in the inverter temporarily on a bench (positive to battery, negative to battery, nothing else)
  3. Walk through the WiFi configuration in the app—you'll need the dongle's serial number
  4. Confirm the inverter appears in the device list and reports at least one data cycle
  5. Only then do I mount it

Here's the thing: the Growatt inverter app is actually pretty solid for remote monitoring, but it assumes you have the WiFi dongle configured correctly. If the dongle isn't talking to your network, the app is useless. And you can't configure the dongle if it's buried behind a panel in a dark compartment.

Checkpoint: The app must show live data before the inverter goes into permanent mounting. No exceptions.

Step 3: Set up error code notifications—then actually investigate them

Growatt inverter error codes follow a pattern: F01 through F20 cover most common faults. Some are harmless blips. Some are warnings. A few mean "shut this down right now."

My rookie mistake: In my first year, I treated all error codes equally. An F03 (AC voltage out of range) I'd investigate immediately. But when I saw an F02 (DC input voltage too high) pop up intermittently on a customer's system, I figured it was a sensor glitch. It wasn't. The panel string was overvoltaging the MPPT tracker during cold mornings. By the time I actually pulled the voltage logs, the MPPT had failed.

That was a $380 part plus $150 in lost rental income for the customer. Total screw-up on my part.

Now here's the protocol I follow, and you should too:

  • F01–F06: Investigate within 24 hours (input/output issues, temperature warnings)
  • F07–F12: Same day intervention (ground faults, overloads, grid interaction problems)
  • F13–F20: Shut down and call support (hardware faults, relay failures, internal faults)

The Growatt inverter app sends push notifications for error codes if you enable them. Enable them. I know one installer who ignored that setting for two years because "I check the portal anyway." He missed three F08 codes (ground fault warnings) that led to a $1,200 repair. The app was literally texting him. He just hadn't clicked the toggle.

Checkpoint: After the first successful data report in the app, go into settings and turn on error code alerts. Then clear your next Saturday morning to review the logs even if there are no alerts.

Step 4: Don't skip surge protection on the RV side

This is the step most DIYers skip because "solar panels don't surge." They're right—panels don't surge. But shore power does, and so do lightning strikes nearby, and so does that cheap generator you plugged into the 30-amp inlet.

In 2021, a customer's trailer got hit by a voltage spike from a campground hookup. It was a 50-amp pedestal with a bad neutral connection—completely the campground's fault. The surge wiped out the converter, the microwave, and the Growatt inverter's input stage. Total damage: $1,400. Not covered by warranty because "surge damage isn't a manufacturing defect."

That's when I started putting a 50 amp surge protector for camper setups on every install. Specifically:

  • Hardwired units go between the shore power inlet and the electrical panel
  • Portable units plug into the pedestal before your shore cord
  • Look for at least 3,000+ joules clamping capacity for a 50-amp setup
  • Confirm the unit is rated for 120/240V split-phase—that's what most 50-amp RV pedestals deliver

For residential or cabin systems, the equivalent protection comes at the electrical panel. A GE Pro 10+2 surge protector is a common choice—it's a Type 2 SPD that installs directly on a breaker. That's 10kA of surge current protection with 2 additional passes through the neutral and ground. For a panel-mounted device on a residential solar setup, that's a solid budget option.

But here's the thing most people miss: a panel-mounted GE Pro 10+2 protects your panel loads. It doesn't protect your inverter on the DC side. So if you're mixing residential-style panel protection with an RV-style solar system, you need two layers—AC side and DC side. I only learned that after a lightning-adjacent event fried an inverter's DC input while the AC side was perfectly protected.

Checkpoint: Every system gets surge protection on the AC input. If you're spending more than $2,000 on an inverter, spend another $150–250 on SPDs. It's cheap insurance.

Step 5: Verify portable power station origins before you integrate them

This one comes directly from customer questions I've fielded hundreds of times: "Where is Jackery solar generator made?"

Fair question. Jackery is a California-based company, but their solar generators are manufactured in China. That matters for a few practical reasons:

  • Warranty service: Shipping a 60-pound unit to a repair depot isn't cheap, even if it's domestic. Some brands have US-based service centers; others require international shipping for repairs.
  • Lead times: If you're integrating a portable power station into a larger system build, know that replacement units or parts can take 2–4 weeks if they ship from overseas.
  • Certifications: A unit sold in the US should have UL or ETL certification—check the label. A unit manufactured for another market might not have the same safety testing.

I made this mistake in late 2023: I spec'd a portable power station into a customer's camper van build without checking the warranty terms. It worked fine for four months, then the inverter board failed. The customer was responsible for return shipping to a service center that turned out to be in Shenzhen. Six weeks round-trip. The customer was not happy, and I ate the cost of a loaner unit.

My advice now: check three things before you commit to any portable power station—where it's manufactured, what the warranty process actually looks like in practice (call the support number and ask), and whether the unit you're getting has US-market certifications on the label.

Checkpoint: Write down the warranty phone number and the average turnaround time before you install the unit into a customer's build. If the phone number goes to a voicemail box that says "please allow 5–7 business days for a response," that tells you something.

Step 6: Document everything (this is the step everyone skips)

I'll keep this short because it's not complicated. But it's the one that's saved me thousands.

Take photos of:

  • Every wire run before it goes behind a panel
  • The inverter's serial number and the dongle's serial number (you'll need both if you ever call Growatt support)
  • The error code screen the first time any code appears
  • The SPD installation before you close up the panel

I keep a shared folder for every install with a simple text file that says: date, customer name, system specs, and "the weird thing that happened." That last field has saved me twice. When a Growatt inverter threw an F20 code eight months after install, I had a note saying it threw an F20 code during initial testing too—just once, then cleared. That context changed the warranty conversation entirely.

Checkpoint: Before you leave the site, you should have at least 20 photos and one text file per system. If you don't, you're not done.

What I'd do differently if I could start over

Looking back, I should have built this checklist in year one instead of year four. At the time, I thought experience meant knowing the answers. Turns out experience actually means knowing the questions to ask before you order parts.

If I could redo my biggest screw-up—that oversized inverter on undersized batteries back in 2020—I'd start with the load calculation spreadsheet on day one. But given what I knew then, I probably would have made the same mistake. Some lessons only stick when they cost you money.

Use the checklist. Skip the invoice.

Price and regulation note: Cost figures in this article are based on my project records from 2019–2025 and vendor quotes from January 2025. Verify current pricing before ordering. Surge protection codes vary by jurisdiction—check with your local authority having jurisdiction (AHJ) for SPD requirements in your area.

Isabel Moreno

Isabel Moreno

Isabel Moreno is a renewable-energy commissioning and operations analyst covering solar EPC handover, SCADA, monitoring platforms, weather stations, inspections, preventive maintenance, troubleshooting, and performance reporting. She uses IEC 62446-1 commissioning practices and IEC 61724-1 monitoring methods while tracking polarity, insulation resistance, string current, I-V behavior, irradiance, module temperature, performance ratio, soiling loss, alarms, availability, and data completeness. Her field guides help EPC teams and asset owners establish traceable baselines, diagnose underperformance, prioritize corrective work, and maintain auditable operating records.